SR 429 has lane and ramp closures for the SR 516 interchange through Nov. 29. SR 408 has lane closures east of town, and Hempel Avenue detours run into mid-December.

Last checked Nov. 19, 2026. This page is updated weekly. Facts come from Florida’s Turnpike Enterprise’s weekly lane closure advisory for Central Florida issued Nov. 13, the Florida Department of Transportation’s work zone data feed (WZDx) as published through FL511, the Central Florida Expressway Authority’s SR 516 project page, SR 429 widening page and construction alerts, and the City of Winter Garden’s Streets page and news alerts.

Winter Garden’s roads belong to several agencies. The City of Winter Garden maintains city streets, Orange County maintains county roads outside the city, the Central Florida Expressway Authority (CFX) runs the SR 429 toll road on the east side of town and is building SR 516, Florida’s Turnpike Enterprise runs the Turnpike to the south, and the Florida Department of Transportation (FDOT) handles state highways such as State Road 50 (West Colonial Drive). For live closures, use FL511 or dial 511.

Who to call

  • Live traffic, closures and crashes: FL511, dial 511
  • City street problems: Winter Garden Public Services, 407-656-2256, or City Hall, 407-656-4111
  • County roads outside the city: Orange County 311
  • SR 516 construction: CFX, 407-505-5594, Construction@CFXway.com
  • SR 429 widening: CFX, 407-487-2474, Design@CFXWay.com
  • Emergencies on the road: 911

This week and Thanksgiving week: Nov. 19 to Nov. 29

SR 429 lane and ramp closures for SR 516. The state’s work zone feed lists single lane closures, ramp closures and detours on SR 429 for project 516-238, the new SR 516 interchange, through Sunday, Nov. 22, and again from Sunday, Nov. 22, to Sunday, Nov. 29. The feed does not say which ramps close on which night. Follow the posted signs and check FL511.

SR 408 overnight full closures are over. The last of the Hempel Avenue bridge closures, on westbound SR 408 between SR 50 (Exit 1) and the Turnpike, was scheduled to end at 6 a.m. Thursday, Nov. 19, the Turnpike’s Nov. 13 advisory said.

Exit 267B is clear. The weekend closure of the Turnpike exit ramps to eastbound SR 50 at Ocoee (Exit 267B) ended Nov. 16. FL511 no longer listed the right lane blocked on the northbound ramp when we checked Thursday evening, Nov. 19. The work adds an outside lane on eastbound SR 50, rebuilds the ramps to fit it and puts a new traffic signal where Turnpike traffic leaves for eastbound SR 50. The Turnpike puts the cost at about $6 million and expects construction to run through early 2027.

The state lists these other closures in and around Winter Garden. Times are Eastern. Dates can change with weather; check FL511 before you leave.

Road Where When What
SR 429 SR 516 interchange work zone (project 516-238) Through Sunday, Nov. 29 Single lane closures, ramp closures and detours
SR 408 Project 408-315, east of town toward downtown Orlando Through Sunday, Nov. 29 Single and double lane closures
Hempel Avenue At SR 408 Into mid-December Road and ramp closures with detours for the bridge replacement

Rain on the roads. Orange County is under a flood watch until 7 p.m. Friday, Nov. 20. FL511 listed water blocking a lane on SR 50 in east Orange County on Thursday; it listed none in Winter Garden. Our flood watch story has the forecast.

Thanksgiving week. The Turnpike’s next weekly advisory, due Friday, Nov. 20, covers the week of Nov. 22. It was not out when we checked Thursday evening. We will add its closures here when it is.

Projects under way

SR 516, the Lake/Orange Expressway. CFX is building a 4.4-mile toll road between U.S. 27 in Lake County and SR 429, in three segments. The segment at the Orange County end (project 516-238) includes a new interchange with SR 429, and that work is behind the SR 429 lane and ramp closures listed above. Construction began in summer 2024; CFX expects a partial opening in spring 2027 and completion in early 2029, its project page says.

Florida’s Turnpike widening, SR 50 to Minneola. The Turnpike is being widened from four lanes to eight and rebuilt between the SR 50 interchange (Exit 272) at the Winter Garden and Clermont line and Minneola, about miles 272.9 to 279.2, the state’s work zone feed says. The Turnpike’s Nov. 13 advisory lists no lane closures on that stretch, and the state’s work zone feed lists none there through Nov. 29. We could not confirm whether the widening is finished.

Hempel Avenue bridge over SR 408. The Hempel Avenue bridge over SR 408, east of Winter Garden, is being replaced. The new bridge will be longer and higher, to make room for SR 408 to be widened to four lanes in each direction, and it gets a sidewalk on each side. The Turnpike puts the cost at about $23 million and expects work to run through early 2027. The state’s work zone feed lists road and ramp closures with detours on Hempel Avenue into mid-December.

SR 429 interchange at Western Way. The Turnpike is rebuilding the SR 429 interchange at Western Way (Exit 8), with new turn lanes, a widened stretch of Western Way and new traffic signals where the ramps meet it. It puts the cost at about $11 million and expects work to run through early 2028. No closures there are listed through Nov. 29.

Projects in design

SR 429 six-laning, Schofield Road to Tilden Road. CFX plans to widen SR 429, the Daniel Webster Western Beltway, from four lanes to six, with new inside lanes and wider median shoulders called Flex Lanes that can carry traffic during emergencies. The project runs in two segments: Schofield Road to New Independence Parkway, and New Independence Parkway to Tilden Road on the south side of Winter Garden. CFX finished the study in fall 2025 and began design in spring 2026; it expects a public meeting and design completion in spring 2027, its project page says. No construction date is set.

City streets

The city’s news alerts list no street closures for the next two weeks as of Nov. 19. The city sweeps its streets Monday through Friday on a four-week rotation, its Streets page says:

  • Week 1: north of Story Road, west of Dillard Street
  • Week 2: north of Story Road, east of Dillard Street
  • Week 3: south of Story Road, east of Dillard Street and Daniels Road
  • Week 4: south of Story Road, west of Dillard Street and Daniels Road

The schedule shifts in heavy leaf-fall season. The city mows its rights-of-way on Mondays, weekly from April through September and every two to three weeks from October through March. For street maintenance, call 407-656-4111, ext. 5448.

What this means for you

  • Using SR 429 at night through Nov. 29? Expect lane and ramp closures near the SR 516 work zone and follow the detour signs.
  • Heading east on SR 408 toward Orlando? The overnight full closures are over, but lane closures continue east of town.
  • Driving Friday? Do not drive through water on a road while the flood watch is in effect.
  • For buses, the airport and parking, see our getting around guide.

Frequently asked questions

How do I check road closures in Winter Garden?

Use FL511 at fl511.com or dial 511 for live closures and crashes on state roads, toll roads and Florida’s Turnpike. City streets are handled by Winter Garden Public Services at 407-656-2256.

Are there closures on SR 429 near Winter Garden this week?

Yes. The state’s work zone feed lists single lane closures, ramp closures and detours on SR 429 for the SR 516 interchange (project 516-238) through Nov. 22 and again the week of Nov. 22 to 29. It does not say which ramps close on which night, so follow the posted signs and check FL511.

Is Turnpike Exit 267B to SR 50 open again?

Yes. The weekend full closure of the exit ramps to eastbound SR 50 at Ocoee (Exit 267B) ended Nov. 16, and FL511 no longer listed the lane blockage on the northbound ramp when we checked Thursday evening, Nov. 19. Construction on the ramps runs through early 2027.

Is SR 429 being widened near Winter Garden?

The Central Florida Expressway Authority plans to widen SR 429 from four lanes to six between Schofield Road and Tilden Road. The project is in design, with a public meeting and design completion expected in spring 2027.

Who do I call about a pothole in Winter Garden?

For a city street, call Winter Garden Public Services at 407-656-2256 or the city’s main line at 407-656-4111. For a county road outside the city, use Orange County 311.