Winter Garden wants a contractor to swap septic tanks near Lake Apopka for city sewer. Proposals are due Jan. 12, and a $6.64 million state grant helps pay.

Winter Garden is looking for a contractor to take a neighborhood beside Lake Apopka off septic tanks and onto city sewer. The city put the Teacup Springs Septic to Sewer Conversion out to bid Friday.

The proposal form lists 133 sewer service connections. A state grant of $6,640,000 is helping to pay for the work.

The city posted the request for proposals, RFP 27-001, on its bid postings page on Nov. 6. A legal notice followed Sunday in the Orlando Sentinel.

Which streets are in it

The construction drawings index in the bid specifications has plan sheets for these streets:

  • North Fullers Cross Road
  • East Fullers Cross Road
  • Tea Garden Court
  • Teacup Springs Court
  • Markel Drive
  • Vic Kay Court
  • Coluso Drive

A new lift station would go just east of North Fullers Cross Road, between Teacup Springs Court and Tea Garden Court. That is according to a 2023 soil study for the project by Andreyev Engineering, which is bound into the specifications. The study says the site is next to the southeast side of Lake Apopka.

Mead & Hunt designed the project for the city, the specifications say.

What the contractor would build

The proposal form sets out the quantities bidders must price. They include:

Work Quantity
New 8-inch gravity sewer pipe 10,040 feet
Sewer service connections 133
Manholes 44
New lift station 1
4-inch force main from the lift station 1,841 feet
New 8-inch reclaimed water main 11,420 feet
Reclaimed water services 155
New asphalt, with base and subgrade 33,400 square yards
Curb 1,800 feet

That means the job also lays reclaimed water lines and repaves the streets it digs up. Some sewer pipe would sit more than 16 feet down, the form shows.

The contract gives the builder 510 days from the start date to reach substantial completion, and 540 days to finish. Late work would cost the contractor $1,000 a day.

Who is paying

The specifications say the project is “funded wholly or in part” by a grant through the Florida Department of Environmental Protection’s Water Quality Improvement program.

The state’s list of 2024-25 Water Quality Improvement grants shows $6,640,000 for the Teacup Springs project. The same list shows $15,000,000 for the city’s Crest Avenue wastewater plant, which is also in line for a separate state loan the City Commission votes on Thursday. We covered that in Winter Garden’s $19.2 million sewer loan vote.

The bid documents do not give a total cost estimate. Contractors fill in their own prices.

Key dates

  • 11 a.m. Tuesday, Dec. 1: mandatory pre-proposal meeting at City Hall, 300 W. Plant St. Firms that skip it are disqualified, the notice says.
  • 2 p.m. Tuesday, Jan. 12, 2027: proposals due at the City Hall reception desk. No faxed or emailed proposals are accepted.

The city will weigh price, past work, staff and equipment, workload and schedule, the notice says. It can reject any or all proposals. The city’s bid page says a recommended award will appear on a City Commission agenda.

What it means for you

If you live on one of the streets above, work cannot start before proposals are in on Jan. 12 and the commission awards a contract. The bid documents set the job’s length, not its start date.

The documents do not say what, if anything, homeowners will pay to connect, or what happens to the old septic tanks. Questions go to City Hall at 407-656-4111.